Important information Are you unable to perform the following steps? Perhaps you don't have the right role or user type. Please contact your organisation's Administrator or click here to read more about roles & user types.
There may be changes within your organisation that require changes to planned audits, for example when an auditor is on holiday or a contract has expired. In this article, you will find a step-by-step plan for making changes.
All changes start with the steps below:
1. Click in the menu bar on Audits & Forms and then on Audit planning
2. Click on Edit planning at the top right
Changes that can be made on a planned audit are:
Deleting
To delete multiple planned audits at once, follow step 1 and step 2 listed at the top of this article.
Follow the steps below:
3. Click on Delete
4. For Assigned to, choose:
a. No auditor: if the audits were assigned to an auditor
b. Auditor: if the audits were assigned to an auditor
5. For Audit definitions, choose:
a. All audits: if you want to delete the audits of all audit definitions
b. Make a selection if you want to delete the audits of one audit definition
6. For Linked to, choose:
a. All clients and objects: if you want to delete the audits of all clients and objects
b. Make a selection if you want to delete the audits of one specific client or object
7. Select the Period
8. Click on Show summary
9. Click on Delete
Moving to unplanned audits
To move audits to unplanned audits, follow step 1 and step 2 mentioned at the top of this article.
Then follow the steps below:
3. Click on Move to unplanned audits
4. For Assigned to, choose:
a. No auditor: if the audits were assigned to an auditor
b. Auditor: if the audits were assigned to an auditor
5. For Audit definitions, choose:
a. All audits: if you want to move the audits of all audit definitions
b. Make a selection if you want to move the audits of one audit definition
6. For Linked to, choose:
a. All clients and objects: if you want to move the audits of all clients and objects
b. Make a selection if you want to move the audits of one specific client or object
7. Select the Period
8. Click on Show summary
9. Click on Delete
10. Click on Move to unplanned audits
Reassign audits
To assign the previously planned audits to another auditor, follow step 1 and step 2 mentioned at the top of this article.
Then follow the steps below:
3. Click on Reassign
4. For Assigned to, choose:
a. No auditor: if the audits were assigned to an auditor
b. Auditor: if the audits were assigned to an auditor
5. For Audit definitions, choose:
a. All audits: if you want to reassign the audits of all audit definitions
b. Make a selection if you want to reassign the audits of one audit definition
6. For Linked to, choose:
a. All clients and objects: if you want to reassign the audits of all clients and objects
b. Make a selection if you want to reassign the audits of one specific client or object
7. Select the Period
8. Click on Show summary
9. Click on Delete
10. Click on Reassign
Take note
Audits can only be assigned to users who have the right to conduct an audit.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article